What is an end-only task?

An end-only task records a single event time instead of a start and end time.

In the Backoffice, when creating or editing a task, you can enable the End-only option to choose whether it tracks a single time or a full start-and-finish duration.

End-only disabled

The task has both Start and Finish timings, so its duration can be measured (for example, Boarding).

End-only enabled

The task records only a Finish time and is treated as a single milestone (for example, Boarding agent arrived at gate).